9/11 Pager Messages

2001-09-11
10:27:31
Metrocall
[100261861]
B
ALPHA
[ 1/ 2] From: Hale, Daphne K. Just a Note: O
2001-09-11
10:27:33
Metrocall
[100261861]
B
ALPHA
n adding a new sub entry, under the reason column, a new dropdown of "targets" have been added. When workers enter substation
2001-09-11
10:27:35
Metrocall
[100261861]
B
ALPHA
for targets, you may now report targets instead of
2001-09-11
10:27:37
Metrocall
[100261861]
B
ALPHA
[ 2/ 2] other. Thanks Daphne Hale
2001-09-11
14:53:16
Metrocall
[100261861]
B
ALPHA
From: GPC plz call me at 6968 Greg M. Smi
2001-09-11
14:53:54
Metrocall
[100261861]
B
ALPHA
From: Williams-Ramsey, Myra B. Ludowici Pri.-Glennville Area #2 46kv line operated @ 13:29. PCB failed to reclose. Closed by Supervisory.Out 2mins & 11secs. Robi
2001-09-11
14:53:55
Metrocall
[100261861]
B
ALPHA
nson, Floyd, Johnson, Bragg, Laurens, DCC, GSOC, notified. STCC
2001-09-11
16:57:33
Metrocall
[100261861]
B
ALPHA
From: Churchwell, John T. @15:28 Bank and Buss Diff at Cartersville 230/115. Test Eng. reports Candlestick destroyed. Test breaker did not test. No load affected. N
2001-09-11
16:57:35
Metrocall
[100261861]
B
ALPHA
otified David Mudd, DCC, Steve Bennett, CCC, MEAG, NTCC.
2001-09-11
17:40:48
Metrocall
[100261861]
B
ALPHA
From: Burks, Katresa C. FYI: Gordon-Sandersville #1 115kv line inst. operated @ 16:33. Cause due to lightning. DCC, CHOATE, SO, GSOC, MEAG, CCC notified.-STCC
2001-09-11
19:01:35
Metrocall
[100261861]
B
ALPHA
From: Wilson, Eugene S. @ 16:58 Cartersville 230kv Bus #2 restored
2001-09-11
19:01:36
Metrocall
[100261861]
B
ALPHA
to normal , 230/115kv Bank "D" still under repair....esw
2001-09-11
21:35:33
Metrocall
[100261861]
B
ALPHA
From: Burks, Katresa C. FYI: N. Americ
2001-09-11
21:35:34
Metrocall
[100261861]
B
ALPHA
us-Pitts 115kv line inst. operated @ 20.22. Cause due to lightning. DCC, Holton, SO, GSOC, MEAG, CCC notified.-STCC